Poured a 30x40 shop slab in Cheyenne and the pump truck gummed up on us
Happened about two weeks ago on a pole barn job, pump operator says the mix was fine but the hopper was clogging every 10 minutes anyway. We lost a good hour and a half and ended up finishing the last 15 feet by hand with a wheelbarrow, which was not how I planned my morning. Got lucky the weather stayed at 68 degrees or that cold joint would have shown up in the finish. Anyone run into a pump clogging when the mix looks fine on paper, or was it just bad luck on our end?
Sounds like the pump operator was real confident right up until his hopper turned into a concrete plug. Mix can test perfect in the lab and still fight you on site if the aggregate is a hair off or the lines aren't primed right. Nothing like finishing the last stretch with a wheelbarrow to really make you question your career choices. At least the weather gave you a break.