Am I the only one who lost 11 days to a window order that got measured wrong?
Ordered custom windows for a build in Ann Arbor back in March and the crew didn't catch that the rough openings were 2 inches off until the truck showed up. The fix meant re-framing three openings plus a 6 week reorder, so the homeowner's move-in slipped from May to almost July. I'm now double checking every opening with a tape before the order goes out, but I'm curious what step you all add to keep this from happening. How are you catching measurement issues before the order leaves the shop?