Framing crew showed up 5 days late in Boise, and I'm still split on whether I handled it right
Standing in a muddy lot off State Street in Boise last October, the framing sub called to say his crew was 5 days behind and would not start until the trusses showed up. I had already paid the deposit for the lumber package and my slab was sitting there curing in the rain. I chose to hold him to the signed schedule and charge the $1,200 a day liquidated damages, which meant he sent a smaller crew out of spite and the job dragged anyway. Part of me thinks I should have just paid a bit more cushion and kept the peace since he is the best framer in the valley. Has anyone found a middle path here, or is it always hold the line or eat the cost?