Learned the hard way that a fixed-price bid from a custom builder in Fresno means nothing without a written allowance list
Signed a build contract with a guy in Fresno last spring at what looked like a locked number, and then the change orders started piling up for stuff I thought was included. Turns out his "appliance package" allowance was $2,800 for a whole kitchen, so every pick was an upcharge and we were $14k over by framing. Get the allowance sheet itemized line by line before you sign anything, down to the door hardware. Has anyone had luck pushing back on a builder to lock those numbers before the contract gets signed?